Case Study – Thermowell Replacement – CSL Biotechnology

CSL BIOTECHNOLOGY MANUFACTURING FACILITY, VICTORIA

PRIVIGEN THERMOWELL REPLACEMENT

CLIENT: CSL BIOTECHNOLOGY

YEAR: 2016

SECTOR: PHARMACEUTICAL

PROJECT SCOPE   Foodline Projects was engaged to replace the thermowell transmitters in 10 different sectors of an operating plant. The project required specialised welders to operate in critical areas with clean and sanitised procedures and equipment to maintain the environments integrity. TECHNICAL EXPERTISE A team of four highly qualified tradesmen completed the project within the required timeline, using highly polished 316 stainless steel pharmaceutical grade tube. Orbital welding was used to weld 150 welds, replacing 90-95 thermowells in situ. During the orbital welding process, Foodline utilised ISO Din collets, a specialised collet for unique pipework sizes in use at the CSL plant. In the critical environment, specialised manual systems were used for weld preparation due to very limited access to some of the critical areas. QUALITY ASSURANCE   Full traceability was mandatory for all fittings and weld maps, coupled with qualifications and drawing updates to CSL standards and QA requirements. Foodline complied with all pharmaceutical QA documentation and performed X-Ray NDT testing on completed welds. All sample welds were reviewed and daily weld tests performed to ensure commitment to quality workmanship in the CSL plant. FINAL OUTCOME Foodline provided highly skilled personnel to ensure the quality of installation was optimal for the client. CSL have commended Foodline on the quality of welds and workmanship.
beenyup smp installation

Case Study – SMP Installation – Beenyup Water Treatment Plant

BEENYUP WATER TREATMENT FACILITY, WESTERN AUSTRALIA

BORE SMP INSTALLATION

CLIENT: KEP RECHARGE ALLIANCE

YEAR: 2016

SECTOR: WATER

PROJECT SCOPE   KEP Recharge Alliance, a joint venture between Thiess and CH2M Hill Australia has started construction works on a $125 million water recycling plant in the northern Perth suburb of Craigie. KEP Recharge Alliance is responsible for the design, construction and commissioning of the Advanced Water Recycling Plant. The partnership between CHT JV and Water Corporation will have a capacity to recharge 14 billion litres of water into groundwater supplies; the scheme will provide a new climate independent water source to boost much needed drinking water supplies. In the future, the scheme can be expanded to ultimately deliver 28 billion litres of water when needed. WATER RECHARGE Once complete, the scheme will recycle water, treat it to drinking water standards and recharge it back into existing groundwater supplies. The Alliance will move more than 18,000 cubic metres of earth before constructing the plant and will then pour 1000cu.m of concrete, install 70km of cables and lay 15km of pipes. The project is scheduled for completion in late 2016 and will have built-in capacity to expand production to 28 billion litres of water as demand increases. AUSTLINE FABRICATIONS INSTALLATION Austline Fabrications has been awarded the installation of all pipe supports, piping, valves and associated instruments to all recharge spooling. Austline committed to a schedule and timeline of mobilisation of bore piping; documentation verification, onsite fabrication and Hydro testing all spooling to AS4041 & AS4037. Austline approached the installation methodically with successful finalisation of all documentation.  

Case Study – Spray Tank Extension – Kukerin

SPRAY TANK EXTENSIONS, WESTERN AUSTRALIA

CLIENT: YARRAMUNDI FARMS

YEAR: 2016

SECTOR: AGRICULTURE

SCOPE OF WORKS Austline Fabrications was engaged by Yarramundi Farms to modify an existing stainless steel chemical tank on a purpose built John Deere self-propelled boom spray. The addition of this modified tank to the machinery extended the capacity to 6000 litres and was fabricated and installed within a 7-day timeline. The client also required an additional stainless steel water tank to replace an existing 400 litre PVC tank which Austline fabricated and installed within the short timeframe. Austline delivered with price competiveness, exceptional quality and exceeded client’s expectation for this project. TECHNICAL SPECIFICATIONS Austline’s tradesmen fabricated the tanks from 316 stainless steel. Within this process TIG welding was primarily utilised, incorporating back to back and purge welding techniques to manufacture the circular tank. Designing and manufacturing the tank to these specifications reduces the opportunity for corrosion internally. This process and design is in line with Sanitary Standards in the industry.

Case Study – Water Farm & Boiler Upgrade – West End Brewery

WEST END BREWERY, SOUTH AUSTRALIA

WATER FARM & BOILER UPGRADE

CLIENT: LION

YEAR: 2013 – 2015

SECTOR: FOOD & BEVERAGE

PROJECT SCOPE WATER FARM The water farm relocation and installation was completed whilst the plant was at full running capacity. To ensure no loss of production, Foodline Projects implemented a phased installation of the new vessels whilst systematically decommissioning and phasing out the old water farm. This included 5 new water vessels and 4 Clean in Place (CIP) tanks. BOILER UPGRADE Two new boilers were installed using 350mm nominal bore steel pipework with the old boilers decommissioned and removed from the site. TEMPORARY WORKS Foodline Projects installed a large amount of temporary pipework to allow continuous production whilst vessels were changed out. These temporary works were then removed at the end of the project. SAFETY FIRST APPROACH The West End brewery upgrade ran for 2 years with 35 specialised welders from TFG Group onsite full time. To ensure the safety of their employees, sub-contractors and operations staff, Foodline Projects employed a dedicated onsite safety officer to oversee the project. As a result, 68,000 man hours were worked with zero safety incidents, MTIs or LTIs. This safety first approach was particularly pertinent given that the total shut down time for the installation was only 7 weeks.

Case Study – Bluetongue Consolidation Project – Warnervale & Abbotsford

BLUETONGUE CONSOLIDATION PROJECT, WARNERVALE & ABBOTSFORD

DISMANTLE & RELOCATION OF CIDER PLANT

CLIENT: CARLTON & UNITED BREWERIES

YEAR: 2014 – 2015

SECTOR: BREWING

WEALTH OF KNOWLEDGE Foodline Projects was engaged by Carlton & United Breweries to uninstall and then mechanically install the plant and equipment from Warnervale to the new cider making facility in Abbotsford. Foodline had comprehensive knowledge of both sites from previous installations and completed the project under budget and within time frame. SCOPE OF WORKS Foodline’s sequential removal was meticulously planned with careful handling of fermenters, bright beer tanks, sugar tanks, pumps and heat exchangers. The successful relocation to Abbotsford required the Foodline team to manage the projects transport, cranage, civil works and packaging to ensure precision installation of all equipment and tanks. Foodline was integral in the commissioning of all relocated equipment once in place at the new cider making plant. AUSTLINE FABRICATIONS TFG Groups Austline Fabrications division in Perth, Western Australia was awarded the design and fabrication of the access platforms, stairs and walkways. Fabricated in the purpose build factory in Welshpool they were then installed on site in Abbotsford to fit the new footprint of the cider making facility. TECHNICAL EXPERTISE Foodline successfully integrated the previous beer fermenters with extensive fabrication and modifications of the valve manifolds to be installed in the new plant as cider fermenters. TFG was chosen for this project due to our ability to sensitively remove utility plants including compressed air, boilers and cooling towers for resale.

Case Study – Stainless Steel Solutions – Water Corporation

WATER SOLUTIONS, WESTERN AUSTRALIA

STAINLESS STEEL SOLUTIONS

CLIENT: WATER CORPORATION

YEAR: ONGOING

SECTOR: WATER

PIT COVERS DM CIVIL, ARMADALE PUMP STATION Austline fabricated and supplied pit covers, safety grates and a stainless steel cast in frame complete with an aluminium cover. All stainless steel items were completely seal welded and passivated as per Water Corporation specifications. Items were inspected by Water Corporation welding inspectors and dispatched with a Water Corporation release form. SAFETY GRATES & ALUMINIUM LIDS GEORGIOU GROUP, KARRATHA WASTE WATER TREATMENT PLANT 10 Austline fabricated and supplied safety grate cast in frames, complete with gasket seal, all hinge pins and accessory items. Austline also supplied aluminium pit covers. Items were completed within the given timeframe to meet the clients deadline and were inspected by Water Corporation weld inspectors prior to dispatch. All items met the clients requirements and specifications. INLET SPECIALS WATER CORPORATION Austline fabricated and supplied multitudes of sizes and quantities, directly to Water Corporation central works. Items were inspected and dispatched to site for Water Corporation contractors to install. PIPE SPOOLING WATER CORPORATION, ARMAGH STREET PUMP STATION Austline fabricated and supplied multiple pipe spools direct to Water Corporation to be used as emergency storage upgrades at the Armagh Street Pump Station. These pipe spools were fabricated using stainless steel 316 materials and were welded to the Australian Standard 4041.